Market
Hudson Yards Maintenance of Equipment Building
Project Details
TUTOR PERINI AFFILIATES
Construction Manager/General Contractor
Contract Amount: $90 Million
Electrical Contractor
Contract Amount: $22 Million
OWNER
ERY TENANT LLC (C/O Related Companies)
LOCATION
New York, NY
ARCHITECT
Kohn Pedersen Fox Architects
SIZE
91,000 Square Feet
COMPLETION
2017
Project Description
The Maintenance of Equipment Building is a two-story, 91,000-square-foot masonry and steel structure building听that includes 46,000 square feet of shop and work areas, 12,000 square feet of administration offices, a 11,000-square-foot rail yard control tower, and a 12,000-square-foot electrical substation.